TEK-Consulting Ltd. Specialized in supplying of equipment and materials of different technical function, covering a wide range of product, which allow realizing large projects.
One of these was the supply of goods in 2015 for the need of “Novo-Salavatskaya Thermal Power Plant”, where the Customer was “ED-Service” Ltd.
The range of supplied goods was various:
- Round forgings, mechanically processed, different nominal size. Delivery period 65 days.
- According to the Customer drawings Injection equipment. Delivery period 35 days.
- Support and suspension system elements. Delivery period 60 days.
- According to the Customer drawings pipe bends. Delivery period 10 days.
- 12X1MP pipes. Delivery period 10 days.
All goods were supplied on time. The quality and completeness were in accordance with the technical requirements of the Russian Federation’s regulatory and technical documentation, as well as with the requirements of the Customer. The packaging complied with the regulations and ensured the safety of the goods during transport and storage. The necessary technical documentation was also provided in the package with all products supplied..